摘要
本文针对大伙房水库输水工程的大坡度斜井有轨运输施工难点,提出井底交叉口处设置车场与设置渣仓两种方案,进行优缺点分析,为类似工程提供参考经验。
In the paper,two plans of setting parking lot and setting muck storage in the intersection at the bottom of shaft are proposed aiming at large slope inclined shaft rail transport construction difficulties in Dahuofang Reservoir Water Conveyance Project. Advantages and disadvantages are analyzed for providing reference for similar projects.
出处
《水利建设与管理》
2016年第4期18-20,共3页
Water Conservancy Construction and Management
关键词
斜井
有轨运输
施工方案
研究
inclined shaft
rail transport
construction plan
research