期刊文献+

西安市第二污水处理厂升级改造工程设计 被引量:7

Design of Upgrading and Reconstruction Project of Second WWTP in Xi'an City
原文传递
导出
摘要 介绍了西安市第二污水处理厂升级改造工程的工艺流程和构筑物设计。工程设计中充分考虑利用原有工程场地,新建多段多级AO池+终沉池,与原有厌氧池+DE氧化沟工艺并行处理污水,总处理量为15×10~4m^3/d。实际运行表明,工程运行效果良好,出水水质达到了《城镇污水处理厂污染物排放标准》(GB 18918—2002)一级A标准。 The process flow and the structure design of the upgrading and reconstruction project of Second WWTP in Xi' an City were introduced. Based on the full use of existing site, the new multistage AO tank and final settling tank were constructed to treat the wastewater along with the original anaerobic tank and DE oxidation ditch. The total treatment capacity was 15 ~ 104 ma/d. The actual operation showed that the treatment effect was good, and the effluent quality could meet the first level A criteria specified in the Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB 18918 - 2002).
作者 杨少斌 刘凯
出处 《中国给水排水》 CAS CSCD 北大核心 2016年第10期48-51,共4页 China Water & Wastewater
关键词 污水处理厂 升级改造 多段多级AO池 WWTP upgrading and reconstruction multistage AO tank
  • 相关文献

参考文献1

  • 1张自杰 林荣忱.排水工程(第4版)[M].北京:中国建筑工业出版社,2000..

共引文献17

同被引文献109

引证文献7

二级引证文献37

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部