富水圆砾层渣土改良与掘进控制技术研究 被引量:4

Soil Improvement and Tunnelling Control Technologies in the Water-rich Round Gravel Layer
下载PDF
导出
摘要 南宁地铁一号线土建五标盾构区间地层以圆砾为主,多次发生刀盘被困及螺旋输送机被卡的现象。在盾构机脱困过程中多次出现沉降过大,甚至产生塌方风险。为解决上述问题,经反复研究、实践,通过向盾构机土仓内添加一定比例的渣土改良溶液,起到增加渣土细颗粒,悬浮圆砾的作用,同时也可防止圆砾大量堆积在土仓内,造成刀盘被困或螺旋输送机被卡。配合渣土改良优化掘进控制技术,解决了盾构机在圆砾地层掘进过程中的诸多难题。 Nanning Metro Line 1 No. 5 Section is mainly covered with round gravel layer, the cutting wheel is often trapped and the screw conveyor is jammed during construction. Some risks such as excessive settlement and collapse are occurred frequently when the shield machine escaping from difficulty. In order to solve the above problems, the project is researched and practiced repeatedly, it is concluded that soil improvement is the key to solve the problem. Round gravel layer is im- proved by adding a certain proportion improving agent in it, it plays a part in increasing fine particles and suspend round gravel, preventing round gravel piling in the soil chamber and trapping the cutting wheel or jamming screw conveyor. By u- sing optimized soil excavation control technology, the improved soil can be transported smoothly in the process of shield ex- cavation.
作者 康洪信
出处 《铁道建筑技术》 2016年第4期73-75,79,共4页 Railway Construction Technology
基金 中国铁建大桥工程局集团有限公司2014年度科技开发项目(Cr13gk-2014-04)
关键词 富水圆砾层 渣土改良 掘进控制 土压平衡盾构机 water-rich round gravel layer soil improvement excavation control earth-pressure balanced shield machine
  • 相关文献

参考文献12

二级参考文献39

共引文献97

同被引文献42

引证文献4

二级引证文献44

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部