宝钢某产线水处理在改造后,水处理构筑物基本未变,增加了过滤器、冷却塔以及污泥处理系统,对各构筑物间的连接管路进行了调整和重新敷设,改造后的水处理始终没有逃脱原规划的缺陷,给日常管理带来了困难。
The Bar Steel Plant of Baosteel after the transformation, water treatment structures remained unchanged. The water treatment system increased filter、cooling tower and sludge treatment. The connecting pipe between the buildings has relayed. But the transformation of the water treatment has not eliminated the defect of the original planning. The defect of the original planning usually makes trouble to the daily management.
出处
《广东化工》
CAS
2016年第9期152-153,共2页
Guangdong Chemical Industry
关键词
宝钢
产线改造
循环水系统
Baosteel
production line reconstruction
circulating water system