摘要 针对郭家河煤矿1306综采工作面切眼因地质条件变化掘进后呈拱状的安装条件,介绍了工作面主要安装设备,分析了工作面安装的准备工作,从液压支架、刮板运输机、采煤机三方面提出了综放工作面设备快速安装的技术途径,实现了1306工作面安装的快速化、安全化、经济化,为类似条件下综放工作面的安装提供了成熟的技术经验。 Because of geological conditions changes in Guojiahe coal mine,the open- off of No. 1306 working face is arched,causing installation difficulty. The paper introduces the main working face installation equipment and the installation preparation, and proposes the technological approaches of fully mechanized caving face rapid installation including hydraulic support,scraper conveyer and coal cutter. Rapid,safe and economic working face installation has been realized with this technology,in 1306 working face of Guojiahe coal mine.
作者 王晓东
出处 《煤炭工程》 北大核心 2016年第5期68-70,共3页 Coal Engineering
关键词 综放工作面 拱状切眼 液压支架安装 刮板运输机安装 采煤机安装 fully mechanized top coal caving faces arched open-off hydraulic support installation scraper conveyer installation coal cutter installation
  • 相关文献

参考文献5

二级参考文献20

共引文献41

同被引文献33

引证文献7

二级引证文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部