摘要 为了研究采场稳定性分析方法与参数优化方法,对夏甸金矿试验采场进行了的工程地质调查、矿岩力学试验、数字测试等工作,获取了表征矿山岩体质量的多种指标。对试验采场岩体质量进行了简要评价,54903采场岩体质量好,55002采场岩体质量一般。根据获取的指标,利用Mathews图表法对试验采场在当前跨度下的稳定性进行了分析,在当前6m进路采场跨度下,采场稳定性程度高,可合理地增大跨度。并根据拟合的稳定-破坏曲线公式求出采场临界跨度,继而综合多因素给出了7m最初跨度设计。利用软岩极限跨度图表法评价出7m设计跨度是经济、安全的。结合FLAC3D数值模拟对图表法应用的准确性进行了对比分析,并最终确定出采场跨度值。 In order to study the method of stability analysis and parameter optimization of stope,several kinds of indexes representing the engineering quality of rock mass in mines were acquired by the survey of engineering geology,the ore-bearing rock mechanics experiments,digital testing etc in Xiadian gold mine.The quality of rock mass is briefly evaluated,including the quality of the 54903 stope is good,and the 55002 stope is normal.According to the acquired index,the stability of stope under the current span was analyzed using the Mathews stability graph method.In the current6 mstope span,the span can be reasonably increased since the stability of stope is higher.The stope stability critical span was concluded by the formula of the fitting-damage curve.Then through the comprehensive consideration of many factors,the initial span is designed as 7m.Based on the graph of soft rock critical span,it is evaluated that the initial span 7mis economical and safe.The application accuracy of the diagram method is briefly discussed by using FLAC3 D and the stope span is finally determined.
出处 《金属矿山》 CAS 北大核心 2016年第5期187-191,共5页 Metal Mine
基金 国家重点基础研究发展计划(973计划)项目(编号:2013CB227902) 国家自然科学基金项目(编号:51174045) 国家自然科学基金重点项目(编号:51034001)
关键词 Mathews稳定图 采场稳定性 参数优化 临界跨度图 数值模拟 Mathews stability graph Stability of stope Parameter optimization Graph of critical span Numerical simulation
  • 相关文献

参考文献3

二级参考文献16

  • 1张娇,姜谙男,易南概,赵德孝.东坪金矿采空区开挖过程的三维有限元数值模拟[J].中国矿业,2006,15(11):81-84. 被引量:11
  • 2布雷迪BHG 布朗ET 冯树仁 余诗刚 朱祚铎泽.地下采矿岩石力学[M].北京:煤炭工业出版社,1990..
  • 3Feng X T, Hudson L The ways ahead for rock engineering design methodologies[J]. International Journal of Rock Mechanics and Mining Sciences,2004,41 ( 2 ) : 255 - 273.
  • 4Feng X T, Hudson J. Rock engineering design [ M ]. Leiden : CRC Press/Balkema,2011.
  • 5Barton N, Lien R, Lunde J. Engineering classifications of rock masses for the design of tunnel support[J].Rock Mechanics, 1974,6 (6) : 189 - 236.
  • 6Mathews K, Hock E, Wyllie D, et al. Prediction of stable excavations for mining at depths below 1000 metres in hard rock[ R ]. Ottawa: Natural Resources Canada, 1980.
  • 7BradyBHG.地下采矿岩石力学[M].3版.佘诗刚,朱万成,赵文,等译.北京:科学出版社,2011.
  • 8Potvin Y. Empirical open stope design in Canada [ D ].Vancouver: University British Columbia, 1988.
  • 9Han S M, Rory H, Zhang Y H. New rock stress factor for the stability graph method [ J ]. International Journal of Rock Mechanics &Mining Sciences,2011,48 ( 1 ) : 141 - 145.
  • 10Bewick R,Kaiser P. Nurmwical assessment of factor B in Mathews' method for open stope design[C]//Proceedings of 3rd CAN-US Rock Mecbanics Symposium. Toronto ,2009 : 1 - 12.

共引文献145

同被引文献62

引证文献11

二级引证文献45

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部