潮间带风电场无过渡段单桩基础施工关键技术 被引量:3

Key technologies for construction of monopile foundation without transition in wind farm in intertidal zone
下载PDF
导出
摘要 在国内第一个潮间带风电场项目——江苏龙源如东150 MW海上风电场一期示范工程中,首次采用了无过渡段单桩作为风机基础。文中通过对该项目实施经验的总结,介绍了潮间带风电场无过渡段单桩基础施工工艺、船舶选型、打桩锤选择、桩身垂直度测量与控制以及施工操作要点等关键技术,可为类似工程施工提供参考。 The pilot works for the first phase of Rudong 150 MWoffshore wind farm was the first domestic wind farm project inthe intertidal zone, and the monopile foundation without transition was used in this project as the wind turbine foundation for thefirst time. By the summary of experience in the implementation of the project, key technologies for monopile foundation withouttransition in the intertidal zone such as the construction technology, selection of ships and hammers, measurement and control ofpile verticality, and the key points of construction and operation were introduced, which will provide a valuable reference forsimilar projects.
出处 《中国港湾建设》 2016年第6期56-59,80,共5页 China Harbour Engineering
关键词 风电 单桩基础 过渡段 钢管桩 wind power monopile foundation transition steel tube pile
  • 相关文献

参考文献4

二级参考文献8

  • 1李刚,祝刘文.卡贝略项目地质钻探报告[R].广州:中交第四航务工程勘察设计院,2013.
  • 2Foundation solutions for projects harbor construction[M]. Luxem- bourg: Arcelor-Mittal, 2007.
  • 3ICE specification for pilling and embedded retaining walls[S].
  • 4周维,周端.桩基施工总结报告[R[.武汉:中交第二航务工程局有限公司,2014.
  • 5中交天津港湾设计院有限公司.工程桩沉桩导向架与固定支撑平台结构计算书[R].2012.
  • 6中交第一航务工程局有限公司.大直径钢圆筒振动下沉设备及工艺的研究与应用[R].2002.
  • 7张连江,孙建波,徐波.移动导向架高精度沉桩技术在外海桥梁工程中的应用[J].中国港湾建设,2015,35(6):46-50. 被引量:9
  • 8范期锦.多台大型液压振动锤联动工作的同步性问题[J].中国港湾建设,2003,23(2):1-4. 被引量:11

共引文献14

同被引文献17

引证文献3

二级引证文献31

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部