基于维修时间窗的柔性作业车间调度优化研究 被引量:15

Research on Optimization of FJSP Based on Maintenance Time Window
下载PDF
导出
摘要 针对柔性作业车间调度和预防性维护的单目标集成优化问题,以最大完工时间为优化指标,建立了基于维修时间窗的集成优化模型,设计了混合"教与学"优化(HTLBO)算法求解该模型。提出一种"基于工序加工时间最短"的机器序列初始化策略,对部分初始种群进行初始优化,以提高部分初始解的质量,使得算法能够以较短的时间收敛。对文献中柔性作业车间调度的基准问题进行求解并比较其计算结果,初步证明该混合算法的可行性;针对集成维修时间窗的柔性作业车间调度优化模型,借鉴文献中的数据生成实例进行求解,并与其他算法进行比较,证明该混合算法的有效性。 An optimization model was proposed to minimize the makespan in FJSP based on maintenance time window,which integrated the preventive maintenance.A hybrid algorithm was presented to deal with the model based on TLBO.A new machine sequence initializing strategy was investigated to optimize partial initial population based on"shortest processing time for operation",which might improve the quality of the initial solutions,so the computing process might convergence in a relatively short time.By calculating and comparing the results of FJSP benchmark problems with other literatures,the feasibility of the hybrid algorithm was proved on the whole.In view of flexible job-shop schedule optimization model which integrated maintenance time window,the data from the literatures was modified for the model and calculated by the hybrid algorithm.By comparing the results with other algorithms,the effectiveness of the hybrid TLBO algorithm was validated.
出处 《中国机械工程》 EI CAS CSCD 北大核心 2016年第10期1337-1343,共7页 China Mechanical Engineering
基金 国家自然科学基金国际(地区)合作与交流项目(51561125002) 国家自然科学基金资助项目(51275190 51575211) 中央高校基本科研业务费专项资金资助项目(2014TS038)
关键词 维修时间窗 柔性作业车间调度问题 “教与学”优化 模拟退火 maintenance time window flexible job shop scheduling problem(FJSP) teaching-learning-based optimization(TLBO) simulated annealing
  • 相关文献

参考文献17

  • 1Naderi B, Zandieh M, Aminnayeri M. Incorporating Periodic Preventive Maintenance into Flexible Flow- shop Scheduling Problems[J]. Applied Soft Compu- ting, 2011,11:2094-2101.
  • 2李林,金琳,周晓军.基于冲击建模的租赁设备预防维护策略[J].计算机集成制造系统,2013,19(1):114-118. 被引量:12
  • 3夏唐斌,奚立峰,周晓军,潘尔顺.串并联衰退系统的多目标预防性维护优化建模[J].计算机集成制造系统,2010,16(4):783-788. 被引量:19
  • 4Ni Jun, Gu Xi, Jin Xiaoning. Preventive Mainte- nance Opportunities for Large Production Systems E Jl. CIRP Annals - Manufacturing Technology, 2015,64. 447-450.
  • 5Fitouhi M-C, Nourelfath M. Integrating Noncyclical Preventive Maintenance Scheduling and Production Planning for a Single Machine[J]. Int. J. Production Economics, 2012,136 : 344-351.
  • 6Allaoui H, Lamouri S, Artiba A, et al. Simultane- ously Scheduling n Jobs and the Preventive Mainte- nance on the Two-machine Flow Shop to Minimize the Makespan [J]. Int. J. Production Economics, 2008,112 : 161-167.
  • 7Li J Q, Pan Q K. Chemical-reaction Optimization for Flexible Job-shop Scheduling Problems with Maintenance Activity[J]. Applied Soft Computing,2012,12(9) 28962912.
  • 8Kacem I, Hammadi S, Borne P. Approach By Lo- calization and Multiobjective Evolutionary Optimi- zation for Flexible Job-shop Scheduling Problems [J]. Applications and Reviews, IEEE Transactions on Systems, Man, and Cybernetics, Part C, 2002, 32(1) : 1-13.
  • 9Pezzella F, Morganti G, Ciaschetti G. A Genetic Algorithm for the Flexible Job-shop Scheduling Problem[J]. Computers Operations Research, 2008,35(10) . 3202-3212.
  • 10Mladenovid N, Hansen P. Variable Neighborhood Search [J]. Computers Operations Research, 1997 24(11) :1097-1100.

二级参考文献19

  • 1奚立峰,周晓军,李杰.有限区间内设备顺序预防性维护策略研究[J].计算机集成制造系统,2005,11(10):1465-1468. 被引量:20
  • 2SHEU S H,GRIFFITH W S.Extended block replacement policy with shock models and used items[J].European Journal of Operational Research,2002,140(1):50-60.
  • 3WANG H Z,PHAM H.Availability and maintenance of series systems subject to imperfect repair and correlated failure and repair[J].European Journal of Operational Research,2006.174(3);l706-1722.
  • 4VAURIO J K.Optimization of test and maintenance intervals based on risk and cost[J],Reliability Engineering and System Safety,1995,49(1):23-36.
  • 5ANISIMOV V V,GURLER U.An approximate analytical method of analysis of a threshold maintenance policy for a multiphase multi-component model[J].Cybernetics and Systems Analysis,2003,39(3):325-337.
  • 6OKOGBAA O G,OTIENO W,PENG X,et al.Transient analysis of maintenance intervention of continuous multi-unit systems[J].HE Transactions,2008,40(10):971-983.
  • 7LAI M T,CHEN Y C.Optimal replacement period of a two-unit system with failure rate interaction and external shocks[J],International Journal of Systems Science,2008,39(1):71-79.
  • 8ZHOU X J,XI L F,LEE J.Reliability-centered predictive maintenance scheduling for a continuously monitored system subject to degradation[J].Reliability Engineering and System Safety,2007,92(4):530-534.
  • 9BARLOW R E,HUNTER L C. Optimum preventive maintenance policies[J].Operations Research,1960,(01):90-100.
  • 10PHAM H,WANG H. Imperfect maintenance[J].European Journal of Operational Research,1996,(03):425-435.

共引文献29

同被引文献103

引证文献15

二级引证文献68

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部