摘要
为了遏制瓦斯超限频发的现象,通过理论研究和工程实践,分析了王坡煤矿瓦斯超限的致灾因素和煤矿在瓦斯超限治理方面尚存在的问题;提出了适合高瓦斯矿井特点的"三区三阶段"采掘规划部署和"一超前三结合"的立体化瓦斯抽采体系;研制了矿井通风智能决策与控制系统;构建了瓦斯超限预警指标体系,开发了瓦斯超限治理综合预警管理平台;形成了"以抽采为核心,以通风为基础,以超限预警为手段,以风险预控管理为支撑"的"一核心三配套"瓦斯治理体系。该体系应用以后,矿井瓦斯超限治理取得明显成效,矿井瓦斯抽采量和抽采率显著提高,瓦斯超限次数大幅下降,2014、2015年连续实现瓦斯零超限治理目标。
In order to contain the phenomenon that gas overlimit frequently occurred,with the theoretical study and engineering practices,the paper analyzed the disaster-causing factors of the gas overlimit and the problems existed in the gas overlimit control of Wangpo Mine.The paper provided the " three blocks and three stages" mining and excavation planning and arrangement suitable to the features of the high gassy mine and the " one advance and three combination" three dimensional gas drainage system.A mine ventilation intelligent decision and control system were researched and developed.A early warning index system of the gas overlimit was established and a comprehensive early warning management platform of the gas overlimit control was developed. " With the gas drainage as a core,the ventilation as a base,the gas overlimit early warning as a means and the risk pre-control management as a support",the gas control system with " one core and three matches" was formed.After the system puting into use,obvious achievements were obtained in the mine gas overlimit control,the mine gas drainage volume and drainage rate were obviously improved,gas overlimit numbers were highly reduced and a zero gas overlimit control target was realized in the year of 2014 and 2015 continuously.
出处
《煤炭科学技术》
CAS
北大核心
2016年第5期145-150,共6页
Coal Science and Technology
基金
国家科技重大专项资助项目(2011ZX05040)
科研院所技术开发专项基金资助项目(2014EG122192)
国家发改委"瓦斯治理示范矿井工程建设"资助项目(发改能源[2012]147号)
关键词
高瓦斯矿井
瓦斯超限
瓦斯治理
超限预警
工作体系
high gassy mine
gas overlimit
gas control
overlimit early warning
work system