试论变电站倒闸操作中接地线安装方法 被引量:1

Discussion on Installation Method of Grounding Wire in Substation Operation
下载PDF
导出
摘要 变电站设备转检修要在设备的各侧合上地刀或装设接地线,当前,大多数的变电站设备装设接地线的方法都是直接连接到引线上,受限于设备的类型,有时装设接地线会比较困难。为解决这个问题,提出了一种接地线的预夹紧装置,并简要介绍其结构和使用,该装置大大降低变电站运行人员在装设地线时的劳动强度,提高工作效率。该方法具有很好的实用价值和推广意义。 The substation equipment maintenance to the equipment in the side of the Shangdi knife or set up the ground wire, at present, most of the substation equipment installation grounding method is directly connected to the lead, limited to the type of equipment, there is a fashion design grounding wire will be more difficult. In order to solve this problem, this paper presents a kind of pre - clamping device of ground wire, and briefly introduces its structure and use, the device greatly reduces the labor intensity of the substation operation personnel in the installation of ground wire, improve work efficiency. This method has good practical value and popularization significance.
作者 章敏
出处 《机电工程技术》 2016年第5期105-108,共4页 Mechanical & Electrical Engineering Technology
关键词 变电站 接地操作要求 接地线 预夹紧装置 应用 substation ground operation requirement ground wire pre clamping device application
  • 相关文献

参考文献5

二级参考文献21

共引文献62

同被引文献13

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部