摘要 针对主动配电网优化运行问题,构建一种全资源优化调度模型,以运行费用最小为优化目标,对分布式发电单元、储能单元、可切除柔性负荷等进行协调调度。针对构建的全资源优化调度模型,采用二次序列规划求解方法,并搭建MATLAB+OpenDSS仿真计算平台。以IEEE37馈线系统作为测试算例,分析不同电价信息下主动配电网采用优化调度后的削峰填谷效果,并进行了对比分析。 In order to realize the optimal operation of active distribution network,an whole resource system optimal scheduling model is established in this paper,controllable distributed energy resources,energy storage systems,and curtailable loads are coordinated,taking the lowest operating cost as the optimization objective.An algorithm based on the sequential quadratic programming and the MATLAB / Open DSS simulation platform are applied to solve the above economic dispatch problem.The model is demonstrated on IEEE 37-bus distribution system.The effect of peak load shifting under the optimal dispatch of active distribution network with different electricity price are analysed,and a comparative analysis is carried out.
出处 《东北电力大学学报》 2016年第3期1-6,共6页 Journal of Northeast Electric Power University
关键词 主动配电网 分布式发电 储能系统 削峰填谷 实时电价 Active Distribution Network Distributed Generation Energy Storage System Peak Load Shifting Real Time Electricity Price
  • 相关文献

参考文献16

  • 1D' Adamo, Christian; Jupe, Samuel ; Abbey, Chad. Global survey on planning and operation of active distribution networks - Update of CIGRE C6.11 working group activities[ C ]. 20th International Conference and Exhibition on CIRED 2009,2009:1-4.
  • 2余南华,钟清.主动配电网技术体系设计[J].供用电,2014,31(1):33-35. 被引量:13
  • 3Pilo F, Pisano G, Soma G G. Advanced DMS to manage active distribution networks [ C ]. PowerTech,2009 IEEE Bucharest,2009:1-8.
  • 4Jim M. Adaptive intelligent power systems:Active distribution networks[J]. Energy Policy,2008,36(12) :4346-4351.
  • 5Simone Paoletti, Marco Casini, Antonio Giannitrapani, et al. Load forecasting for active distribution networks [ C ]. 2011 2nd IEEE PES Inter- national Conference and Exhibition on Innovative Smart Grid Technologies (ISGT Europe) ,2011:1-6.
  • 6Mingbo L, Tso S K, Ying C. An extended nonlinear primal-dual interior-point algorithm for reactive-power optimization of large-scale power systems with discrete control variables [ J ]. Power Systems, IEEE Transactions on, 2002,17 (4) :982 -991.
  • 7Liu M B, Canizares C A, I-Iuang W. Reactive Power and Voltage Control in Distribution Systems With Limited Switching Opera-tions [ J ]. Power Systems, IEEE Transactions on,2009,24 (2) :889-899.
  • 8Feng-Chang L, Hsu Y-Y. Fuzzy dynamic programming approach to reactive power/voltage control in a distribution substation[ J]. Power Sys- tems, IEEE Transactions on, 1997,12 (2) :681-688.
  • 9Hsu Y-Y, Feng-Chang L. A combined artificial neural network-fuzzy dynamic programming approach to reactive power/voltage control in a distribution substation [ J ]. Power Systems, IEEE Transactions on, 1998,13 (4) : 1265-1271.
  • 10Roytelman I, Wee B K, Lugtu R L, Voh/var control algorithm for modern distribution management system [ J ]. Power Systems, IEEE Transac- tions on,1995,10(3) :1454-1460.

二级参考文献112

共引文献334

同被引文献54

引证文献5

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部