摘要
本文针对福州地区某个前期已安装20k W光伏的屋顶发电项目,利用美国NASA气象网站的气象数据,应用HOMER软件和Matlab仿真生成该地区的全年风速和太阳光照强度曲线,考虑离网和并网两种情况,配置了垂直轴风机和蓄电池容量,为该楼宇风光储联合发电系统的规划提供参考。
This paper based on an installed 20kW photovoltaic power generation project, using the meteorological data of NASA's meteorological sites and software of HOMER and Matlab to obtain annual curve of global solar and wind speed. Then considering the situation of off-grid and on-grid to configure the capacity of vertical axis wind turbine and battery, provides a reference for the planning of building wind/PV/storage hybrid power generation system.
出处
《电气技术》
2016年第5期26-30,共5页
Electrical Engineering
关键词
楼宇风光储
容量优化配置
离网
并网
building wind/PV/storage hybrid power generation system
capacity optimization and configuration
off-grid
grid-connected