摘要
针对高松树隧道涌水流砂地层施工的重难点,提出了以堵为主与以排为主两种施工方案,通过分析两者的优缺点,选取了以排为主的施工方案,并阐述了具体的施工措施,确保了施工质量与安全。
According to the important and d ifficult points in the water and quicksand stratum of Gaosongshu Tunnel, the paper points out the block-oriented and drainage-oriented construction schemes, selects the former one by comparing their advantages and disadvantages, and il lus-trates the construction measures, so as to ensure the construction quality and safety.
出处
《山西建筑》
2016年第18期148-149,共2页
Shanxi Architecture
关键词
隧道
涌水流砂地层
超前支护
掌子面
tunnel, water and quicksand stratum, advanced support, tunnel face