摘要
通过对山西省中部引黄工程勘探试验洞Ⅰ标在隧洞施工过程中出现的涌水的分析,制定了"堵水,稳定地层"的处理方案,并对处理涌水过程中的有关要求和相应工艺等方面的内容进行明确,实现了解决该处涌水问题的目的,为在后续施工中遇到类似的涌水情况提供处理经验。
Water shut-off and stratum stabled treatment schemes were established with analysis of water gushing appeared in the Central Yellow River Diversion Project in Shanxi Province,and the requirements and corresponding technology were also definite. It accomplished the purpose of solving water gushing problem and provided experiences for similar situations in the subsequent constructions.
出处
《山西水利科技》
2016年第2期39-41,共3页
Shanxi Hydrotechnics
关键词
中部引黄工程
隧洞涌水
注浆封堵
the Central Yellow River Diversion Project
tunnel water gushing
grouting