某大桥承台大体积混凝土温控分析

Temperature Control of Mass Concrete Construction of Fuping railway bridge
下载PDF
导出
摘要 某大桥26#墩承台施工,采用低热水泥,并掺入矿物、粉煤灰、引气剂和高效减水剂,降低水化热,增强混凝土强度、耐久性;分层浇筑、铺设冷循环水管,增强混凝土散热能力,降低混凝土内部温度;在施工过程严格实行控温保温养护措施,进行实时温度监测,实现了大体积混凝土温度控制的信息化施工,为混凝土保温保湿养护提供依据,为同类工程提供参考价值。 The mass concrete construction of number 26 pile cap of the Bridge makes use of low heat cement,mixed with mineral,fly ash,air-entraining agent,and concrete water-reducer to cut down the hydration heat as well as enhance the concrete strength and durability.Reducing the internal temperature of the concrete by setting circulating cooling water pipes and stratified pouring.The implementing of strict temperature control,preservation measures and real-time dynamic temperature monitoring in the working process makes the information construction of mass concrete temperature control come true.The study provides reference to the heat and humidity preservation of concrete and other similar projects.
作者 范倩倩
机构地区 长沙理工大学
出处 《吉林水利》 2016年第6期18-21,共4页 Jilin Water Resources
关键词 大体积混凝土 承台 温度控制 温度监测 mass concrete pile cap temperature control temperature monitoring
  • 相关文献

参考文献6

二级参考文献11

共引文献114

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部