摘要 惠州东江水利枢纽工程闸坝砂砾卵石地基采用振冲碎石桩加固处理,取得了较好的经济效益。对振冲碎石桩复合地基承载力采用载荷试验检测,得出复合地基承载力特征值,并计算出变形模量,为工程设计提供了可靠依据。试验表明:振冲碎石桩复合地基的承载力特征值为300 k Pa,满足设计要求。就复合地基静载荷试验检测结果进行分析,为同类工程试验检测分析提供了参考。 The sluice dam foundation composed with sand and gravel of the East River Hydro-Junction Project in Huizhou is treated by vibro replacement stone column and obvious economic effect is achieved. The characteristic value of beating capacity and deformation modulus of the composite foundation are obtained by static load test to provide a basis for engi- neering design. The static load test shows that the characteristic value of bearing capacity of the composite foundation is 300kPa meeting design requirements. In the paper, the static load test results are analyzed for similar project reference.
出处 《资源环境与工程》 2016年第3期339-343,373,共6页 Resources Environment & Engineering
关键词 闸坝 砂砾卵石地基 振冲碎石桩 载荷试验 惠州东江水利枢纽 sluice dam alluvial sand and gravel foundation vibro replacement stone column static load test the East River Hydro-Junction Project in Huizhou
  • 相关文献

参考文献4

  • 1潘享永,可洪有,王殿春.广东惠州东江水利枢纽工程初步设计报告:3工程地质[R].广州:广东省水利电力勘测设计研究院'2004.
  • 2中华人民共和国住房和城乡建设部.建筑地基处理技术规范:JGJ 79-2012[S].北京:中国建筑工业出版社,2013.
  • 3南京水利科学研究院.土工试验规程:SL 237-1999[S].北京:中国水利水电出版社,1999.
  • 4潘亨永,李智英.阳江抽水蓄能电站下水库主坝坝基载荷试验分析[J].人民珠江,2015,36(1):108-112. 被引量:4

二级参考文献3

  • 1SL237-1999.土工试验规程.[S].,..
  • 2广东省水利电力勘测设计研究院.广东阳江抽水蓄能电站可行性研究报告[R].广州:广东省水利电力勘测设计研究院,2006,7.
  • 3东南大学,浙江大学,湖南大学,等.土力学.3版.北京:中国建筑工业出版社.