摘要
引汉济渭二期工程某隧洞出现塌方现象,施工单位对塌方段能否处理和后续隧洞能否继续开挖提出异议,分析塌方现象、塌方段洞室附近地质条件及塌方原因,得出对塌方工程处理是可行的,后续隧洞加强支护是可以成洞的结论。
One tunnel of Hanjiang River to the Weihe River Project Phase Ⅱ occurred landslide, so construction unit questioned whether the collapse section can be treated and follow-up of the tunnel can continue to be dug or not. Based on the consideration of collapse and the geological conditions of the collapse area, this article analyses the causes of land-slides. Therefore, it obtains the conclusion that the treatment of landslide area can be carried out. So, the tunnel can continue to be dug through the method of strengthening the support and protection.
出处
《资源环境与工程》
2016年第3期480-482,共3页
Resources Environment & Engineering
关键词
隧洞
塌方
原因分析
tunnel
landslide
cause analysis