考虑鲁棒性的Max-npv项目调度问题 被引量:11

Max-npv project scheduling problem considering robustness
原文传递
导出
摘要 为应对复杂环境下的不确定性因素对项目净现值产生的不利影响,本文提出现金流关键度(CFC)分散缓冲法,在现金流惩罚因子较大的活动前设置时间缓冲,实现由于活动延迟给项目净现值造成的损失最小化,并保证项目现金流支付尽可能按原计划执行.为验证该方法的有效性和可行性,在相同约束条件下,将之与Max-npv非鲁棒性优化模型进行对比分析.仿真实验结果表明,在低、中、高三种不确定性程度下,CFC分散缓冲法不仅在净现值相关绩效指标上有更优的结果,而且具有较好的鲁棒性. The cash flow criticality (CFC) scattered buffer procedure is introduced to cope with the adverse effects on the net present value (NPV) of project, which are caused by uncertainties in complicated environment. Through inserting time buffer in front of activities with greater cash flow weight, a robust model is constructed to minimize the loss of NPV, as well as the payment plan of project is implemented as planned as well as possible. In order to verify tile effectiveness of the method, the Max-npv non- robust schedule is generated by simulated annealing (SA) to provide the comparable results. Simulation experimental results show that the method of CFC is not only superior to SA in the indictors of NPV in the low, medium and high degree of uncertainty, but it also has better robustness.
出处 《系统工程理论与实践》 EI CSSCI CSCD 北大核心 2016年第6期1462-1471,共10页 Systems Engineering-Theory & Practice
基金 国家自然科学基金(71271097)~~
关键词 净现值 鲁棒性项目调度 分散缓冲 现金流关键度 net present value robust project scheduling scattered buffer cash flow criticality
  • 相关文献

参考文献21

  • 1Russell A H. Cash flows in networks[J]. Management Science, 1970, 16(5): 357-373.
  • 2何正文,徐渝,朱少英.Max-npv项目进度问题研究评述[J].管理工程学报,2005,19(4):60-63. 被引量:24
  • 3Vanhoucke M, Demeulemeester E, Herroelen W. Progress payments in project scheduling problems[J]. European Journal of Operational Research, 2003, 148(3): 604-620.
  • 4He Z W, Wang N, Jia T, et al. Simulated annealing and tabu search for multi-mode project payment scheduling[J]. European Journal of Operational Research, 2008(3): 688-696.
  • 5Zhu G, Bard J, Yu G. Disruption management for resource constrained project scheduling[J]. JournM of the Operation Research Society, 2005, 56(4): 365-381.
  • 6Buss A H, Rosenblatt M J. Activity delay in stochastic project networks[J]. Operations Research, 1997, 45(1): 126-139.
  • 7何正文,徐渝.工程项目支付进度优化:一个案例研究[J].管理工程学报,2008,22(1):67-71. 被引量:5
  • 8Van de Vonder S, Demeulemeester E, Herroelen W, et al. The trade-off between stability and make span in resource-constrained project scheduling[J]. InternationM Journal of Production Research 2006, 44(2): 215-236.
  • 9Baroum S M, Patterson J H. The development of cash flow weight procedures for maximizing the net present value of a project[J]. Journal of Operation Management, 1996, 14(3): 209-227.
  • 10Al-Fawzan M A, Haouari M. A bi-objective model for robust resource-constrained project scheduling[J]. Inter- national Journal of Production Economics, 2005, 92(2): 175-187.

二级参考文献48

  • 1何正文,徐渝,朱少英.Max-npv项目进度问题研究评述[J].管理工程学报,2005,19(4):60-63. 被引量:24
  • 2何正文,徐渝,朱少英.具有奖励惩罚结构的项目支付进度问题研究:双重角度[J].系统工程理论与实践,2005,25(10):39-45. 被引量:23
  • 3张静文,徐渝,何正文,柴国荣.项目调度中的时间-费用权衡问题研究综述[J].管理工程学报,2007,21(1):92-97. 被引量:24
  • 4Kolisch R, Padman R. An integrated survey of deterministic project scheduling[ J ]. Omega, 2001, 29 (3) : 249 - 252.
  • 5Herroelen W, Leus R. Project scheduling under uncertainty: Survey and research potential[ J ]. European Journal of Opera- tional Research, 2005, 165 (2) : 289 - 306.
  • 6Demeulemeester E, Herroelen W. A branch-and-bound procedure for the multiple resource-constrained project scheduling problem[J]. Management Science, 1992, 38(12) : 1803 -1818.
  • 7Yamashita D S, Armentano V A, Laguna M. Scatter search for project scheduling with resource availability cost[ J]. Euro- pean Journal of Operational Research, 2006, 169 : 623 - 637.
  • 8De P, Dunne E J, Ghosh J B, et al. The discrete time-cost tradeoff problem revisited [ J ]. European Journal of Operational Research, 1995, 81(2): 225-238.
  • 9Elmaghraby S. Activity nets: A guided tour through some recent developments [ J]. European Journal of Operational Re- search, 1995, 82(3) : 383 -408.
  • 10De P, Dunne E J, Ghosh J B, et al. Complexity of the discrete time-cost tradeoff problem for project networks[ J]. Opera- tions Research, 1997, 45 (2) : 302 - 306.

共引文献34

同被引文献111

引证文献11

二级引证文献35

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部