摘要
以丹灶工业大道燃气工程为例,分析了在城区内进行水平定向钻施工时,为减少对周边交通和环境的影响,经过方案的比选合理解决预拖管道的临时摆放问题。
In this paper, the author considers that the position of placing pipe is a construction difficulty of pipe crossing project in urban areas. Taking Danzao Industrial Avenue gas pipe project tbr example, it mainly describes how to confirm a reasonable path of placing pipe after scheme comparison.
出处
《上海煤气》
2016年第3期13-15,共3页
Shanghai Gas