摘要 结合近年来我国现有码头结构加固改造工程实例,通过全面、系统的分析,形成码头加固改造成套技术,为码头结构加固改造的设计和施工提供安全、适用和示范性的技术方法。同时,为构建一整套更加系统完备、科学规范、运行有效的技术体系提供借鉴。 Combining with existing wharf structure reinforcement projects in recent years, we carry out a comprehensive and systematic analysis and put forward a complete set of technology for the strengthening and renovation of the wharf structure, which can provide a safe, suitable and exemplary technical method for the wharf structure reinforcement designing and construction.Meanwhile, it provides reference for building up a complete set of more systematic, scientific and standardized and effective technology system.
出处 《水运工程》 北大核心 2016年第6期174-182,共9页 Port & Waterway Engineering
关键词 加固改造 高桩码头结构 重力式码头结构 板桩码头结构 关键施工技术 wharf reinforcement pile wharf structure gravity quay structure sheet pile wharf structure key construction technology
  • 相关文献

参考文献5

  • 1常勤,彭玉生,祝振宇,等.全国沿海港口码头结构加固改造工作专题调研报告[R].北京:交通运输部水运局,中交水运规划设计院有限公司,2013.
  • 2吴辉,顾宽海,李增光.分离式码头加固改造结构:中国专利,ZL201120098179.0[P].2012-04-11.
  • 3王轩.天津港老旧码头加固和加深改造[J].港工技术,2011,48(1):29-31. 被引量:10
  • 4边树涛,宓宝勇.重力式码头结构加固改造设计探讨[J].中国港湾建设,2014,34(8):23-26. 被引量:10
  • 5顾宽海,李增光,程泽坤.一种加固型重力式沉箱码头结构:中国,ZL201220705068.6[P].2013-06-12.

二级参考文献7

  • 1JTS167-2-2009重力式码头设计与施工规范[S].
  • 2程明波,陈继丹,李莉元.提高重力式码头靠泊能力的结构改造方法[J].水运工程,2007(8):67-69. 被引量:2
  • 3深圳妈湾电厂专用卸煤码头改造工程[R].广州:中交第四航务工程勘察设计院有限公司,2011.
  • 4广州港南沙港区二期工程码头结构加固改造工程方案设计[R].广州:中交第四航务工程勘察设计院有限公司,2012.
  • 5厦门港海沧港区一期工程4号、5号泊位码头结构加固改造工程[R].广州:中交第四航务工程勘察设计院有限公司,2012.
  • 6湛江港#300码头技术改造工程施工图设计[R].广州:中交第四航务工程勘察设计院有限公司,2008.
  • 7吴今权,杨丽民.关于小泊位靠大船问题的探讨[J].港工技术,2009,46(6):7-10. 被引量:3

共引文献16