广州周大福金融中心施工电梯数量计算方法的探索与应用 被引量:1

Exploration and Application of Construction Elevators Calculation Method at Chow Tai Fook Finance Center in Guangzhou
下载PDF
导出
摘要 提出采用"粗算精验"理论的施工电梯数量确定方法,即先按粗算法经验公式计算所需施工电梯的总数,做平面及立面的具体规划后,再按估算的人数及物资量,通过提出的精算法复核验证施工电梯运输能力与工程实际运输需求的匹配程度,从而达到优化配置施工电梯的目的,提高了施工组织策划的科学性。 The method to determine the amount of construction elevators proposed in this paper adopts the theory of ‘rough estimate and precision inspection '. Firstly,the amount of construction elevators is calculated according to the method of rough estimate. After the specific planning at plan or profile is determined,matching degree between traffic capacity of construction elevators and the actual transportation demand is checked with the method of precision inspection according to the estimated workers and goods amount. This method achieves the objective of optimal allocation of construction elevators and improves the scientificalness of the construction organization plan.
出处 《施工技术》 CAS 北大核心 2016年第12期38-41,46,共5页 Construction Technology
关键词 高层建筑 施工电梯 计算方法 拟合公式 tall buildings elevators calculated method fitting formula
  • 相关文献

参考文献6

二级参考文献19

  • 1三栖邦博.超高层办公楼.刘树信译.北京:中国建筑工业出版社,2003.
  • 2翁如壁.现代办公楼设计.北京:北京市建筑设计研究院,1995.
  • 32009JSCS-J全国民用建筑工程设计技术措施[J].规划·建筑·景观,(2009).
  • 4胡玉银.第四讲:超高层建筑施工垂直运输体系的构成与配置(一)[J].建筑施工,2007,29(8):632-634. 被引量:6
  • 5中国建筑科学研究院建筑机械化研究分院.GB50310-2002电梯工程施工质量验收规范[S].北京:中国建筑工业出版社,2002:12.
  • 6江苏省华建建设股份有限公司,江苏邗建集团有限公司.JGJ33-2012建筑机械使用安全技术规程[s].北京:中国建筑工业出版社,2012.
  • 7胡玉银.第四讲:超高层建筑施工垂直运输体系的构成与配置(三)[J].建筑施工,2007,29(10):814-816. 被引量:8
  • 8叶浩文,顾国荣,季万年.广州国际金融中心施工[M].北京:中国建筑工业出版社,2011.
  • 9张琨.单塔多笼循环运行施工电梯:中国,CNl03145019A[P],2013-06-12.
  • 10崔晓强,张松,李子旭,林海,沈新华.广州珠江城关键施工技术[J].建筑施工,2011,33(10):877-879. 被引量:1

共引文献50

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部