摘要
详细介绍了西澳洲某铁矿干料系统试车,从试车前的准备到带负荷试车,包括安装检查,预试车,单体试车,无负荷联动试车,带负荷联动试车等阶段,对试车过程中出现的问题进行了分析,并提出了解决方案。
Commissioning of primary crushing system for certain iron ores in Western Australia, which starts from precommissioningpreparation and ends at on-load trial run, is introduced in detail. This commissioning includes five stages, whichare erection inspection, pre-trial run, single unit trial run, off-load trial run and on-load trial run. Problems arising from thiscommissioning process are analyzed and corresponding solutions are also put forward.
出处
《矿业工程》
CAS
2016年第3期41-43,共3页
Mining Engineering