摘要
叙述了菲律宾联合熔炼与精炼公司(PASAR)转炉电除尘器的安装过程,该电除尘器在特定条件下采用预组装-整体吊装的方法,本文详细介绍了安装方案及吊装方案。
The paper described installation of converter ESP in PASAR.The pre-assembling and integral hoisting method was adopted for installation of ESP under specific conditions.The installation and erection solutions were introduced in details in this paper.
出处
《中国有色冶金》
CAS
北大核心
2016年第3期51-56,共6页
China Nonferrous Metallurgy
关键词
转炉
电除尘器
预组装
吊车安全负荷
定位焊
converter
ESP
pre-assembling
safe load of crane
positioned welding