盖梁预应力工程施工过程优化研究 被引量:2

Study on Optimization of Prestressed Engineering Construction Process of Bent Cap
下载PDF
导出
摘要 通过Midas-FEA有限元分析系统对沌口互通式立体交叉主线桥左幅24#盖梁预应力工程施工过程进行优化,研究发现对大悬臂盖梁预应力筋采用一次张拉方式并且在盖梁与桥墩交界处添加钢筋网片,不仅可保证工程质量,而且可大幅缩短工期以及设备占用时间。 The finite element analysis system Midas-FEA is used to optimize the prestressed engineering construction process of bent cap No.24 of the left main bridge for the Zhuankou Interchange Project. The study finds that the one-time tension mode used for the prestressed tendon of large-cantilever bent cap and the steel reinforced meshes added at the junction of bent cap and bridge pier cannot only guarantee the engineering quality, but also greatly shorten the construction period and the occupation time of the equipment.
作者 王琼 牛万芬
出处 《城市道桥与防洪》 2016年第7期190-194,21,共5页 Urban Roads Bridges & Flood Control
关键词 盖梁 预应力工程 施工过程 优化 bent cap prestressing engineering construction process optimization
  • 相关文献

参考文献1

  • 1桂满树,高德志,姜毅荣,等.MidasFEA操作指南与基本例题[z].北京:北京迈达斯技术有限公司.

同被引文献4

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部