李雅庄矿复合顶板巷道锚索破断原因分析

Reason Analysis of Anchor Cable Breakage in Compound Roof Roadway of Liyazhuang Coal Mine
下载PDF
导出
摘要 李雅庄矿6122巷为复合顶板巷道,在掘进过程中出现了大面积的锚索破断现象,针对该情况进行了锚索力学性能测试、巷道顶板岩层窥视,同时结合巷道支护情况,最终确定该巷道锚索破断的原因为:锚索力学性能不稳定,部分锚索力学性能指标不符合行业标准要求;巷道顶板2.0 m位置有一处明显的离层,而顶锚杆长度为2 m,导致锚索在该位置受拉伸和剪切复合应力影响易破断。把锚杆长度改为2.4 m后,没有出现锚索破断现象,巷道支护效果有了明显改善。 The phenomenon of a large area of anchor cable breakage in advancing is appeared on Liyazhuang coal mine 6122 compound roof roadway. In view of the situation,anchor rope mechanics performance testing,roadway roof strata peek is carried out. At the same time combines the condition of roadway support,eventually determines the reason of roadway anchor cable breakage. The anchor cable mechanical performance is instability,some of the indexes do not conform to the requirements of the industry standard. The position of roadway roof 2. 0 m has a obvious abscission layer,but the roof bolt length is 2 m. It leads to anchor easy to fracture in the location influenced by tensile and shear stress. After changing the anchor length to 2. 4 m,the phenomenon of anchor cable breakage does not appear.Roadway supporting effect has a improved significantly.
作者 白润江
出处 《山西焦煤科技》 2016年第4期43-45,共3页 Shanxi Coking Coal Science & Technology
关键词 复合顶板 锚索 破断 力学实验 岩层 窥视 Compound roof Anchor cable Breakage Mechanics experiment Rock stratum Peep
  • 相关文献

参考文献6

  • 1国家质量监督检验检疫总局,中国国家标准化管理委员会.GB/T228.1-2010金属材料拉伸试验第一部分:室温试验方法[S].北京:中国标准出版社,2011:11-20.
  • 2R·H·Chowdhury,王家臣.沿着岩石不连续面多重破坏的概率模型(续)[J].露天采矿,1988(4):44-46.
  • 3覃政刚.高强预应力锚杆的锚固机理及时效性分析[D].武汉:中国科学院武汉岩土力学研究所硕士论文,2009.
  • 4康红普.煤矿深部巷道锚杆支护理论与技术研究新进展[J].煤矿支护,2007(2):1-8. 被引量:55
  • 5Chen S, Fu C, Isam S. Finite element analysis of jointed rock masses reinforced by fully-grouted bolts and shotcrete lining [J]. International Journal of Rock Mechanics and Mining Sciences,2009,46 (1) :29 -30.
  • 6林健,康红普.螺纹钢树脂锚杆的研究现状与趋势[J].煤矿开采,2009,14(4):1-4. 被引量:37

二级参考文献14

共引文献89

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部