摘要
惠阳污水厂二期扩建,把原来的CAST工艺改为倒置A2/O工艺,用二氧化氯代替紫外消毒,出水达到出水都达到国家《城镇污水处理厂污染物排放标准》(GB18918-2002)的一级B标准。该工艺节省土地和投资费用。本文讲述该厂扩建前后的工艺设计和设备参数、设计要点和运行情况。
Huiyang wastewater plant phase ii expansion is that the inverted A^2/O process is used instead of the original CAST process,and disinfection with chlorine dioxide instead of ultraviolet.The effluent from new process can meet the national " urban sewage treatment plant pollutant discharge standard "(GB18918-2002) standard of level 1 B.The inverted A^2/O process can save land and investment cost.This paper tells the plant before and after the expansion of the process design and equipment parameters,key points of design and operation.
出处
《山东化工》
CAS
2016年第13期205-208,共4页
Shandong Chemical Industry