摘要
介绍了西安地铁2号线延长线自动售检票(AFC)系统接入原有已运行系统时,AFC系统与综合监控系统在综合联调中的对接联调方法。通过搭建模拟测试环境、增加冗余服务器、调整联调时间等方法解决2号线延长线AFC系统接入已正常服务的综合监控系统时存在的AFC联调时间紧张、延长线与一期工程数据点表不一致等难题,在不影响现有系统正常运营的情况下实现了延长线AFC与综合监控数据的互联互通,为国内在建的同类型延长线接入工程提出了建设性的思路。
The measures of docking and debugging between AFC system and ISCS during the commissioning phase on the extension line of Xi′an Metro Line 2 are introduced.Through the platform of simulation testing environment,adding redundant servers and other methods,problems existed in the docking and debugging between AFC system and ISCS which are in normal service on the extension line of Xi′an Lines 2 are solved.This method has realized the interconnection between AFC on the extension line and the ISCS data without affecting normal operation of the existing system,providing a construction idea for the docking and debugging project of the extension metro line built in China.
出处
《城市轨道交通研究》
北大核心
2016年第7期87-91,共5页
Urban Mass Transit
关键词
地铁延长线
自动售检票系统
综合监控系统
对接联调
metro extended iine
automatic fare collection(AFC)
integrated supervision control system(ISCS)
docking and debugging