针对龙里草原风电场搭接35kV龙湾线并网发电对龙里电网稳定运行、电压无功控制带来一定影响的现状,供电企业采取措施加强电网调度管理,协同龙里风电场积极采取动态无功补偿等措施消除并网带来的不利影响,确保电网安全稳定运行。
Longli Wind Power Plant' s access to the 35 kV longwan line had influence on the grid stable operation and voltage reactive control of Longli power grid, power supply enterprise took measures to strengthen the power grid dispatching management and eliminate the negative influence through taking dynamic reactive power compensation measures to ensure the safety and stable operation of power grid.
出处
《贵州电力技术》
2016年第6期11-12,57,共3页
Guizhou Electric Power Technology
关键词
风电并网
潮流计算
电网调度
无功补偿
wind power grid
power flow calculation
power grid dispatching
reactive power compensation