基于时间参数表的RSM图绘制方法 被引量:4

Approach of RSM Diagram Drawing Based on Time Parameter Table
下载PDF
导出
摘要 RSM图是开展重复性建设项目进度控制与优化的基础,但现有绘制方法还不够理想。确定各工序系的最佳执行模式,不仅可得到各工序最佳施工持续时间,还可保证RSM图与实际施工的一致性;建立各工序系的时间参数表,包含施工持续时间、开始和完成时间、停工时间等,只需简单的表上计算,将各工序系初始生产线向右"平移"即可得到其最终生产线,从而快捷、准确地绘出满足工序系逻辑及搭接关系、资源限制条件的RSM图;定义各工序系的控制数组,结合时间参数表,通过简单的表上操作,可确定RSM图上的控制序列并区分工序种类,为重复性建设项目管理提供了充分信息。通过一个案例详细说明了基于时间参数表绘制RSM图的具体步骤。 RSM diagram is the foundation of scheduling control and optimization in repetitive construction project, yet the existing methods are still not good enough. The optimal resource utilization option of each activity group is identified to obtain the duration of each activity and assure consistency between RSM diagram and practical construction situation. Time parameter table, which includes the information of duration, start and finish time, interruption time, is established. Then, RSM diagram can be abtained quickly and accurately by simply calculating on time parameter table and shifting initial production line. The obtained RSM diagram has satisfy precedence and overlapping relationships, resource availability constraints. To provide sufficient information for project management, controlling array is defined to specify the controlling sequence and types of activities through operation on time parameter table. An example application is presented to illustrate the specific steps of drawing RSM diagram based on time parameter table.
出处 《土木工程与管理学报》 北大核心 2016年第4期18-23,共6页 Journal of Civil Engineering and Management
基金 国家自然科学基金(51408459) 陕西省自然科学基金(2014JM7296)
关键词 RSM图 时间参数表 控制数组 控制序列 RSM diagram time parameter table controlling array controlling sequence
  • 相关文献

参考文献15

  • 1Vanhoucke M. Work continuity constraints in project scheduling [ J ]. Journal of Construction Engineering and Management, 2006, 132(1) : 14-25.
  • 2Hegazy T, Kamarah E. Efficient repetitive scheduling for high-rise construction [J]. Journal of Construction Engineering and Management, 2008, 134 (4) : 253-264.
  • 3Hegazy T. Computer-based Construction Project Man- agement [ M ]. Upper Saddle River: Prentice Hall, 2002.
  • 4张立辉,潘楚云,邹鑫.重复性项目调度与网络模型转化方法研究[J].管理科学学报,2014,17(6):49-59. 被引量:6
  • 5Dressler J. Construction management in West Germany [J]. Journal of the Construction Division, 1980, 106 (4) : 447-487.
  • 6Johnston D W. Linear scheduling method for highway construction [J]. Journal of the Construction Division, 1981, 107(2) : 247-261.
  • 7Harris F C, Evans J B. Road construction-simulation game for site managers [ J ]. Journal of the Construction Division, 1977, 103(3):405-414.
  • 8Reda R. RPM : repetitive project modeling[ JJ. Jour- nal of Construction Engineering and Management, 1990, 116(2) : 316-330.
  • 9蒋根谋,熊燕.线性计划方法及其应用研究[J].华东交通大学学报,2008,25(5):8-11. 被引量:8
  • 10Harris R B, Ioannou P G. Scheduling projects with re- peating activities [J]. Journal of Construction Engi- neering and Management, 1998, 124(4) : 269-278.

二级参考文献47

  • 1蒋根谋.一种新的线性工程项目进度计划的编制方法[J].铁道建筑,2005,45(11):87-89. 被引量:4
  • 2Yam in R. A., Harmelink D. J. Comparison of Linear Scheduling model (ISM) and Critical Path Method (CPM) [ J]. Journal of Construction Engineering and Management, 2001,127(5) : 374 - 381.
  • 3Chrzanowski, E. N. and Johnson, D. W. Application of Linear Scheduling [J]. Journal of Construction Engineering and Management, 1996, 112(4) :476- 491.
  • 4Johnston, D. Linear Scheduling Method for Highway Construction[ J]. Journal of Construction Engineering and Management, 1981,107(2): 247 - 261.
  • 5Vorester, M. C., Beliveau, Y. J., and Bafna, T. Linear Scheduling and Visualization[ J ]. Transportation Research Record, 1992,135 (1) :32 - 39.
  • 6Harmelink D.J., Rowings J. E. Linear scheduling Model:Development of Controlling Activity Path [ J]. Journal of Construction Engineering and Management, 1998,124(4) :263 - 268.
  • 7Kris G. Mattila and Dulcy M. Abraham Resouce Leveling of Linear Scheduling Using Integer Linear Programming [J]. Journal of Construction Engineering and Management, 1998,124 (3) : 232 - 244.
  • 8Harris R B, Ioannou P G. Scheduling projects with repeating activities[ J]. Journal of Construction Engineering and Manage- ment, 1998, 124(4): 269-278.
  • 9Arditi D, Tokdemir O B, Suh K. Effect of learning on line-on-balance scheduling[ J ]. International Journal of Project Man- agement, 2001, 19:265 -277.
  • 10Arditi D, Tokdemir O B, Suh K. Scheduling system for repetitive unit construction using line-of-balance technology[ J]. Engineering Construction and Architectural Management, 2001, 8 (2) : 90- 103.

共引文献13

同被引文献15

引证文献4

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部