摘要
以有限元方法为基础,对新疆吐鲁番二塘沟水利枢纽工程的土石坝进行了三维仿真计算,并对堆石体和心墙在竣工期和满蓄期的应力应变极值进行了分析。分析结果表明,该土石坝的设计是合理的,堆石体和心墙不会发生拉压破坏或剪切破坏;心墙底部向两侧发生大约7 cm的轻微侧胀,成为比较危险的部位,在设计和施工中应予以高度重视。
In this paper, it conducts the three-dimensional simulation calculation on the earth and rockfill dam of Ertanggou hydro-project in Sinkiang Turpan based on the finite element method , and analyzes the stress-strain extreme values of rockfill body and core-wall after the completion period and full storage period. The result shows that the design of the earth and rockfill dam is reasonable , the rockfill body and core-wall won’t appear tension-compression damage and shear failure. At the bottom of the core-wall, it appears about 7cm slight inflation towards to both sides and which makes it become the dangerous place. So we should pay more attention to the design and construction process.
出处
《黄河水利职业技术学院学报》
2016年第2期8-11,共4页
Journal of Yellow River Conservancy Technical Institute
基金
黄河水利职业技术学院校内科研基金:深厚覆盖层上沥青混凝土心墙坝应力应变仿真分析(2014QNKY013)
关键词
新疆吐鲁番二塘沟水利枢纽
土石坝
应力应变
三维仿真
本构模型
Sinkiang Turpan Ertanggou hydro-project
earth and rockfill dam
stress-strain
three-dimensional simulation