期刊文献+

M701F4重型燃气轮机主要系统安装阶段的清洁度控制

下载PDF
导出
摘要 以三菱日立的M701F4重型燃气轮机为例,结合工程中出现的各种问题,介绍了天然气管道系统、进气过滤系统和润滑油系统在安装阶段保证清洁度的必要性和检查要点,并针对天然气管道系统提出了改进建议,经工程实践证明效果良好。
作者 常兵
出处 《机电信息》 2016年第21期162-164,共3页
  • 相关文献

参考文献5

  • 1蒋洪德,任静,李雪英,谭勤学.重型燃气轮机现状与发展趋势[J].中国电机工程学报,2014,34(29):5096-5102. 被引量:150
  • 2GB50973--2014联合循环机组燃气轮机施工及质量验收规范[S].
  • 3主机厂资料.燃气一蒸汽联合循环机组天然气管道吹扫规程[Z].
  • 4主机厂资料.进气过滤器检查规范[z].
  • 5主机厂资料.M70IF4燃气一蒸汽联合循环多轴机组润滑油系统冲洗规程[z].

二级参考文献23

  • 1Bancalari E,Chan P,Diakunchak I S.Advanced hydrogen gas turbine development program[C]//ASME Turbo Expo 2007:Power for Land,Sea,and Air.American Society of Mechanical Engineers,2007:977-987.
  • 2Advanced IGCC/H2 Gas Turbine Development[R]. European Commission:Framework Programmes for Research and Technological Development,2006.
  • 3EU Technology Platform,Recommendations for RTD,support actions and international collaboration priorities within the next FP7 energy work program in support of deployment of CCS in European [R]. European Commission:The EU Technology Platform for Zero Emission Fossil Fuel Power Plants,2008.
  • 4Bemtgen J.FP7 Energy-Call 2008 information and brokerage Day,FP7 innovation and energy technology[R]. European Commission:Framework Programmes for Research and Technological Development,2008.
  • 5Chen W,Ren J,Jiang H.Effect of turning vane configurations on heat transfer and pressure drop in a ribbed internal cooling system[J].Journal of Turbomachinery,2011,133(4):041012.
  • 6Xiang W,Chen S,Xue Z,et al.Investigation of coal gasification hydrogen and electricity co-production plant with three-reactors chemical looping process [J].International Journal of Hydrogen Energy,2010,35(16):8580-8591.
  • 7Wan K,Zhang S,Wang J,et al.Performance of humid air turbine with exhaust gas expanded to below ambient pressure based on microturbine[J].Energy Conversion and Management,2010,51(11):2127-2133.
  • 8Zhang X W,Wang Y R,Xu K N.Flutter prediction in turbomachinery with energy method[J].Proceedings of the Institution of Mechanical Engineers,Part G:Journal of Aerospace Engineering,2011,225(9):995-1002.
  • 9Fischer R,Ratliff P,Garbett P.SGT-8000H Product Validation at Irsching4 Test Center[C]//Power-Gen Asia 2008,Kuala Lumpur,Malaysia,2008.
  • 10Hada S,Tsukagoshi K,Junichiro Masada,et al.Test Results of the World’s First 1600C J-series Gas Turbine[J]. MHI Technical Review,2012,49(1):18-23.

共引文献149

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部