高阶段矿石溜井快速形成技术研究 被引量:4

Study on Fast drifting Technology of High-level Ore Chute
原文传递
导出
摘要 矿石溜井是采场出矿的关键工程,其施工速度直接关系到采场的回采进度。为加快大红山铁矿大结构采场回采进度,提出采用天井钻机施工一条直径Φ1.4 m、高200 m的天井,然后采用吊罐法自下而上扩刷成Φ3 m的阶段矿石溜井。现场应用表明,天井钻机扩帮法成井速度达到80m/月,较普通法成井速度快77.8%,较吊罐法成井速度快45.5%,成井速度显著提升。 The ore chute is a crucial project in ore drawing and its drifting speed has a direct effect on the normal mining progress. To speed up the mining progress of large stope in Dahongshan iron mine, the raise boring machine was pro- posed to excavate a chute with diameter of 1.4 m, and height of 200 m. Then, the diameter of this chute was expanded to 3 m from bottom to top by cage raising method. Field appli- cation indicated that the drifting speed was improved obvi- ously and reached to 80 m per month by this method, which had a 77.80% increase than the common method and 45.5% than the cage raising method.
出处 《矿业研究与开发》 CAS 北大核心 2016年第8期21-23,共3页 Mining Research and Development
基金 国家科技支撑计划项目(2013BAB02B06)
关键词 高阶段 矿石溜井 天井钻机 快速掘进 High level, Ore chute, Raise boring machine,Rapid drifting
  • 相关文献

参考文献9

二级参考文献39

共引文献70

同被引文献132

引证文献4

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部