摘要
根据某建筑工程的实际情况,对主楼与地库相连部位取消沉降后浇带进行地基变形验算,并采取了跳仓法施工技术,实践证明跳仓法既能够解决取消后浇带引起的裂缝及沉降问题,又可以节省工期,节约造价。
According to the fact in some architectural project,the paper undertakes the foundation deformation calculation at the settlement postpouring belt of the connection of the main building and basement,adopts the sequence construction technique,and proves the method can solve the cracks and settlement caused by cancelling the post-pouring belt,so as to shorten the construction period and save cost.
出处
《山西建筑》
2016年第24期37-38,共2页
Shanxi Architecture
关键词
跳仓法
后浇带
沉降值
筏板
sequence method
post-pouring belt
settlement value
raft plate