摘要
介绍了矿井主运输系统改造工程方案设计的主要内容,采用设计方案进行施工,节约了矿务工程量,并减少了系统整体停机时间,阐述了主斜井带式输送机机身延伸及张紧基础加固改造的技术创新,为神东矿区以后类似改造工程提供了借鉴经验。
Introduces the main transport system main content of engineering design ,using the design scheme for construction,saving the mines of quantities, and reducing the overall system downtime greatly ,the paper explains the technological innovation of the main belt conveyor's extension and the reinforcement transformed of the tensioning device's foundation,providing reference for the similar project of shendong mining area in the future.
出处
《煤矿机械》
2016年第8期115-118,共4页
Coal Mine Machinery
关键词
刮板输送机
滚筒
主运输系统
改造设计
scraper coveyer
roller
main transport system
transformed design