摘要
对某火力发电厂试运行期间运煤系统出力低、达不到额定出力的现象进行分析,提出了相应的解决措施,解决了实际问题,为类似工程故障的处理提供了参考经验。
This paper analyzes the cause of insufficient coal handling system output during a thermal power plantcommission. Some treatment measures are proposed, and the practical problem is solved out. Reference experience isprovided for the treatment of similar engineering faults.
出处
《机械工程师》
2016年第8期194-195,共2页
Mechanical Engineer
关键词
运煤系统
带式输送机
出力
落煤管
导料槽
coal handling system
belt conveyor
output
coal chute
skirtboard