介绍了深圳地铁1号线香蜜湖至车公庙承力索换线的施工方案,并针对承力索放线施工时所涉及到的主要施工难点,提出相应的解决方法,对今后类似换线施工提供指导。
Introduces the construction plan of replacement of messenger wires between Xiangmihu and Chegongmiao in line 1 of Shenzhen Metro, puts forward the relative solution measures with regard to the main construction difficulties involved in the messenger wire stringing, provides guidance for similar wire replacement and construction in the future.
出处
《电气化铁道》
2016年第4期43-46,共4页
Electric Railway
关键词
柔性架空接触网
承力索
架线
施工方案
flexible overhead catenary system
messenger wire
stringing
construction plan