摘要
随着“走出去”“走进去”国家战略的实施,众多的国内电建公司承接到国外电站项目,尤其是‘一带一路’上的优质项目.本文以哈萨克斯坦冬季高寒地带进行的水压试验为实际案例进行注意事项的论述以及关键点的安排,为类似的项目执行提供参考.
As more and more Chinese companies have signed and will execute the power plant projects overseas, it is very challenging to perform the work especially to have the hydraulic test in winter Season of rough area, this paper illustrate the typical example successfully demonstrated in this case.
出处
《环球市场信息导报》
2016年第25期97-98,共2页
Global Market Information Guide