大直径顶管定向穿越高压铁塔技术研究 被引量:2

Study on Technology of Large Diameter Pipe Jacking Crossing High Pressure Tower
下载PDF
导出
摘要 文章对顶管顶进地面沉降机理和原因进行分析,将压密注浆技术成功应用于顶管土体加固,以改善土质性能;同时,通过合理的施工控制技术和监测技术,从设计、施工、监测多个角度有效地控制了地面沉降变形,保证了铁塔安全,可为类似大直径顶管穿越既有构造物基础提供参考。 This article analyzed the mechanism and reason for surface subsidence of the pipe jacking construction. The compaction grouting technology was successfully applied in pipe jacking soil consolidation, which could improve the soil properties. At the same time, using the reasonable construction control technology and monitoring technology, it controlled effectively the surface subsidence deformation from the multiple aspects of design, construction and monitoring, which ensured the safety of the tower. It could be taken as reference for similar large diameter pipe jacking crossing existing structures.
出处 《现代交通技术》 2016年第4期53-58,共6页 Modern Transportation Technology
关键词 顶管 压密注浆 施工控制 施工监测 pipe-jacking compaction grouting construction control construction monitoring
  • 相关文献

参考文献2

共引文献2

同被引文献19

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部