印尼帕卡特水电站竖井压力钢管,竖井约130m,该工程在洞内施工,受场地、设备和施工道路的限制,施工条件复杂,任务重,工期紧,难度大,不安全因素多。本文根据笔者多年的现场施工经验对其安装方案进行分析。
The shaft is about 130 m aiming at shaft pressure steel pipe in Indonesia Packard Hydropower Station. The project is constructed in the tunnel,which is limited by site,equipment and construction roads. It is characterized by complicated construction conditions,heavy construction task,tight construction period,high construction difficulty and many unsafe factors. In the paper,the installation plan is analyzed according to site construction experience of the author for many years.