上石盘电航枢纽泄洪闸基础处理与消能防冲设计 被引量:2

Foundation Treatment and Design of Energy Dissipation and Scouring Prevention of Flood Sluice,Shangshipan Project
下载PDF
导出
摘要 上石盘电航枢纽工程坝址地质条件差、泄洪流量大、运行工况及水力学条件复杂,采用覆盖层大开挖岩基建闸结合消力戽消能的设计方案,较好地适应了闸址自然条件和枢纽的运用要求,节省了工程量和投资。经水力计算和模型试验验证,戽流消能在中、小洪水下泄时处在稳定水跃区运行,较大洪水下泄时对下游冲刷影响较小。 As the weak geological condition at dam site,high flood discharge,complicated operating and hydro-mechanic conditions of Shangshipan project,the design featuring large overburden excavation,gate built on bedrock and bucket energy dissipator satisfies the natural conditions at gate site and requirements of the project operation as well as both work quantity and investment are reduced. Through hydraulic calculation and model test verification,the bucket flow energy dissipation can operate in the stable hydraulic jump area when both large and small floods are discharged. The larger flood discharged slightly scours the downstream.
出处 《西北水电》 2016年第4期38-43,共6页 Northwest Hydropower
关键词 砂卵砾石覆盖层 软岩地基 基础处理 闸室结构 戽流消能 水工模型试验 overburden of sand cobble and gravel soft rock ground foundation treatment chamber structure flow energy dissipation hydraulic model test bucket gate
  • 相关文献

参考文献8

  • 1邱敏,鹿宁,鲍呈苍,周邠鹏,赵靖伟.桩基在多布水电站厂房深覆盖层地基中的应用[J].西北水电,2014(1):44-48. 被引量:3
  • 2中华人民共和国水利部.水闸设计规范:SL265-2001[S].北京:中国水利水电出版社,2001:27-33.
  • 3中华人民共和国住房和城乡建设部.建筑桩基技术规范:JGJ94-2008[S].北京:中国建筑工业出版社出版.2008.
  • 4中华人民共和国住房和城乡建设部.建筑地基处理技术规范:JGJ79-2012[S].北京:中国建筑工业出版社,2013.
  • 5国家电力公司华东勘测设计研究院.混凝土重力坝设计规范:DL 5108-1999[S].北京:中国电力出版社,2000.
  • 6李炜.水力计算手册[M].2版.北京:中国水利水电出版社,2006.
  • 7武汉大学.嘉陵江上石盘电航枢纽工程水工泥沙整体模型试验研究报告[R].2011.
  • 8四川大学.嘉陵江上石盘电航枢纽工程水工单体模型试验研究报告[R].2013.

二级参考文献2

共引文献34

同被引文献25

引证文献2

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部