摘要
介绍了千万吨级煤矿综采工作面地理和设备情况,从倒架的经过、原因分析、处理和预防四个方面进行阐述,得出预防倒架最合理有效的办法是在正确的支护下,尽量快地向前推进工作面,这对新型千万吨级矿井工作面倒架的预防和处理具有一定的参考价值和指导意义。
The paper introduces the geography and equipment of the fully-mechanized mining face of a ten-million-ton coal mine,in terms of the process,cause analysis,treatment,and precaution of support dumping accident,and concludes that the most reasonable and effective method to prevent the support dumping is to advance the working face as soon as possible under the correct support.The study has some reference value and guidance for the prevention of the support dumping in new ten-million-ton mines.
出处
《山西煤炭》
2016年第3期27-29,共3页
Shanxi Coal
关键词
千万吨
综采工作面
倒架
事故分析
ten-million-ton
fully-mechanized mining face
support dumping
accident analysis