摘要
文章介绍了RCM的来源以及实施RCM检修的必要性,阐述了RCM分析方法和RCM维修体系之间的关系。通过与传统RCM分析方法比较,详细介绍了一种适合一般工程技术人员使用的RCM分析方法,即COFA分析方法,以及如何用该方法建立一个动态的RCM维修体系。另外通过与AP913设备可靠性管理流程对比,阐述了RCM分析在以可靠性为中心的维修体系中的重要性。
This paper introduced the origin and necessity of RCM. The relation between RCM approach and RCM program was also explahled. As one of the classic RCM approaches, COFA approach,which is much more suitable for engineers in power -plants, was detailed in this paper by comparing to traditional RCM approaches. The RCM Living Program based by COFA was also introduced. The importance of the RCM approach in a RCM program was emphasized by comparing the RCM Living Program based by COFA to the Equipment Reliability Process Description (AP-913).
出处
《中国核电》
2016年第3期267-273,共7页
China Nuclear Power