针对数学优化方法在露天矿进度计划应用中存在的只对单一时段计划进行优化,或是对多时段计划进行分段优化,没有实现全时段整体优化的问题,在前后时段0-1整数规划和大小时段0-1整数规划两种模型分段优化的前期工作基础上,提出了露天矿整体优化的0-1整数规划模型,并针对计算速度慢的问题,提出了相应的改进措施.该模型既实现了多时段生产计划的整体优化,又解决了分段优化无解的隐患,还保证了速度和精度,不仅可实现用下层计划验证上层计划,而且可用于由下层计划导出上层计划,其实用性和通用性更好.
To solve the integrative optimization of multi-period plans in the applications of open pit production only focused on single-period or multi-period optimization with mathematical optimization methods,a 0-1 integer programming model for the integrated optimization was proposed on the basis of previous works of 0-1 integer programming models for "before and after"periods and for "large and small"periods. The corresponding improvement measures were put forward for lowcomputing speed. The model realizes the integrative optimization of multi-period plan,avoids the potential danger of no solution to the discrete optimization,and also guarantees the computational speed and accuracy. The model can be used to verify upper plan with lower plan and to derive upper plan from lower plan,and shows a better adaptability and versatility.
作者
孙效玉
邓鹏宏
赵明
SUN Xiao-yu DENG Peng-hong ZHAO Ming(School of Resources &Civil Engineering, Northeastern University,Shenyang 110819, China Resources Planning Management Department, Ansteel Mining Company, Anshan 114 004,China Open-Pit Mine Engineering Business Unit,CCTEG Shenyang Engineering Company, Shenyang 110 015,China)
出处
《东北大学学报(自然科学版)》
EI
CAS
CSCD
北大核心
2016年第10期1460-1464,共5页
Journal of Northeastern University(Natural Science)
基金
"十二五"国家科技支撑计划项目(2015BAB15B01)
国家自然科学基金创新研究群体项目(71321001/01)
关键词
露天矿
生产进度计划
0-1整数规划
线性规划
整体优化
多时段
open-pit mine
production scheduling
0-1 integer programming
linear programming
integrative optimization
multi-period