摘要 核电厂概率安全评价(PSA)可以论证核电厂的风险满足安全目标,也是对运行核电厂进行风险管理的有效工具,例如核电厂的在役检查、安全分级、技术规格书优化等。核电厂的风险指引管理是在确定论的基础上,充分利用概率安全评价的结果进行风险影响评价,以此来论证决策的合理性。核电厂的重要设计改进通常基于传统的工程分析结果,没有分析其对核电厂整体风险的影响。重点探讨风险指引决策的基本原则以及方法,以核电厂设计改进实例探讨如何在分析时引入风险指引方法,并提出相关建议。 The probabilistic safety analysis( PSA) can demonstrate that if the risk of nuclear power plant satisfies the safety goals,and also can be used in the risk management of nuclear power plant to improve in- service test,classification of equipment and maintenance etc. The risk- informed management of nuclear power plant is the combination of determinate methodology and probabilistic methodology. In the comprehensive decision,the PSA results should be used to evaluate the risk and demonstrate the rationality. The design improvements of nuclear power plant are usually based on the traditional engineering analysis,and the influences for the overall risk are not considered. This paper specially introduces the basic principles and methods of risk- informed management and discusses how to use the risk- informed method to analyse the design improvement of nuclear power plant and put forward related suggestions.
出处 《工业安全与环保》 北大核心 2016年第9期64-67,共4页 Industrial Safety and Environmental Protection
关键词 风险指引 核电厂设计改进 概率安全评价 risk-informed design improvement for nuclear power plant(NPP) probabilistic safety analysis(PSA)
  • 相关文献

参考文献14

二级参考文献51

  • 1王朝贵,郭建兵.大亚湾核电站全厂断电事故及第5台应急柴油机的概率安全评价[J].核动力工程,2004,25(4):324-327. 被引量:13
  • 2景建国,戴忠华.状态检修在核电站设备管理中的作用[J].中国电力,2004,37(8):31-34. 被引量:4
  • 3王海涛,吴宜灿,刘萍,张士杰,胡丽琴,李亚洲.概率截断对PSA中RAW重要度的影响研究[J].核科学与工程,2006,26(4):363-367. 被引量:13
  • 4USNRC.An Approach for Using Probabilistic Risk Assessment in Risk.Informed Decisions on Plant-Specific Changes to the Licensing Basis[R].RGI.174,Revision1.2002.
  • 5USNRC.An Approach for Plant-Specific,Risk-Informed Decision-making:Technical Specifications[R].RGl.177.1998.
  • 6USNRC.Use of Probabilistic Risk Assessment in PlantSpecific.Risk.Informed Decision.making:GeneralGuidance.Chapter 19 of Standard Review Plan(Revi-sion 1)[R].NUREG-0800.2002.
  • 7IAEA.Living Probabilistic Safety Assessment(LPSA)[R].IAEA-TECDOC-1106.1999.
  • 8IAEA.Procedures for Conducting Probabilistic Safety Assessments of Nuclear Power Plants(Level 1)[R].IAEA Safety Series NO.50-P-4.1 92.
  • 9ASME.Standard for Probabilistic Risk Assessment for Nuclear Power Plant Applications[S].ASME RA-S-2002.
  • 10USNRC 10 CFR 50.65. Requirements for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants[S]. 2003.

共引文献27

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部