针对宝中线牵引变电设备和接触网设备进行了适应性分析和计算,结合牵引供电系统负荷急剧增加的问题,给出了切实可行的改造方案,希望能为其他同类既有电气化铁路扩能改造项目提供一定的参考。
With regards to adaptive analysis and calculation for system equipment for Bao-Zhong railways, with combination traction power supply equipment and overhead of fierce increment of traction power supply feasible and applicable reconstruction plan has been put forward, hoping to provide certain references on other expansion and reconstruction of existing electrified railways contact r loads, similar
出处
《电气化铁道》
2016年第5期14-17,22,共5页
Electric Railway
关键词
既有线
电气化
扩能改造
Existing railway
electrification
capacity expansion and reconstruction