地铁施工期间交通疏解方案优化研究 被引量:5

Study on Optimization of Traffic Reconciliation Scheme during Metro Construction
下载PDF
导出
摘要 地铁车站通常设置于道路交叉口等车流和人流较为集中的区域,且因地铁施工周期长,施工期间对道路交通影响较大,制定交通疏解方案是保证路面交通有序、稳定运行的关键。针对济南市轨道交通R3线盛福庄站,设计了施工期间的两种交通疏解方案,并综合考虑各因素,利用AHP层次分析法,对两种方案进行了评价比选。 The metro station is normally set up in the area where the vehicle flow and pedestrian flow of road intersection are centralized. The determination of traffic reconciliation scheme is the key to guarantee the ground traffic in order and stable operation because of long metro construction period and large influence on road traffic during construction. Aiming at Shengfuzhuang Station in Rail Traffic R3 of Jinan City, two traffic reconciliation schemes are designed during design, and various factors are comprehensively considered. The analytic hierarchy process(AHP) is used to evaluate, compare and select two schemes.
出处 《城市道桥与防洪》 2016年第10期19-22,7,共4页 Urban Roads Bridges & Flood Control
关键词 地铁施工 交通疏解 AHP层次分析 metro construction traffic reconciliation analytic hierarchy process(AHP)
  • 相关文献

参考文献8

二级参考文献20

共引文献11

同被引文献12

引证文献5

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部