高水头深孔事故闸门的原型动水闭门试验 被引量:1

Prototype Closing Test in Flowing Water for Deep Emergency Gate with High Water Head
下载PDF
导出
摘要 某工程孔板洞和排沙洞弧门设计水头分别达到140 m和122 m,高水头引起高压力、高流速,为了有效排沙,要求闸门频繁局部开启,由此给该工程弧门结构设计带来一系列研究课题。笔者结合该工程事故闸门的原型动水闭门试验情况及产生原因进行详细介绍、分析,对泄水建筑物的通气孔设施设计提出建议。 The design water head is 140 m for the gate of orifice tunnel and 120 m for that of desilting tunnel of a project. High water head results in high pressure and high flow rate, and gates shall be often partially opened for effective desilting. Therefore, a number of issues shall be studied in structural design of the gate. This paper studies the prototype closing test in flowing water for emergency gates of the project and the causes, and provides suggestions for design of air holes of water release structures.
出处 《红水河》 2016年第5期6-8,16,共4页 Hongshui River
基金 河南省交通运输厅科技项目(2012P51) 河南省教育厅重点科技项目(14B580001)
关键词 事故闸门 动水试验 原型试验 通气孔 emergency gate flowing water test prototype test air hole
  • 相关文献

参考文献4

二级参考文献1

  • 1王成 邵敏.有限单元法基本原理与数值方法[M].北京:清华大学出版社,1988.51-91.

共引文献5

同被引文献9

引证文献1

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部