摘要
研究无线闭塞中心(RBC)设备在枢纽车站应用的设计原则及西安枢纽RBC的实现措施。通过分析枢纽车站的特点和难点,并结合西安北枢纽工程实例,对运营场景进行详细分析与研究,并综合考虑枢纽车站站型及线路特点,提出RBC交权点、RBC等级转换点的设置方案及基本设计原则,为类似的工程设计及实施提供一定的借鉴。
The paper analyzed design principles of Radio Block Center (RBC) equipment applied in hub station and its implementation measures in Xi'An Northern hub station. Combined with engineering experience of Xi'An Northern hub station, through analysis on characteristics and difficulties of the hub station itself, the design principles and setting schemes of RBC control scope transfor- mation point and grade transformation point were put forward. It will benefit for future similar engineering design and provide a reference and guidance significant during implementation.
出处
《自动化与仪器仪表》
2016年第8期125-127,共3页
Automation & Instrumentation
关键词
无线闭塞中心
RBC等级转换
RBC交权
hub station
radio block center
RBC grade transformation
RBC control scope transformation