简要介绍老挝南欧江七级水电站可研阶段选定的混凝土面板堆石坝枢纽布置方案,经过工程招标等后续工作,工程即将开工,可研阶段的设计技术将在实践中进一步得到验证和考验。
This paper gives a brief introduction to the concrete face rockfill dam complex layout selected in the feasibility stage of the Nam Ou River-7 hydropower project. The construction of the project will commence soon after completion of public bidding and follow-up work and the design completed at the feasibility study stage will be verified and tested in its implementation practice.
出处
《云南水力发电》
2016年第5期88-92,共5页
Yunnan Water Power
关键词
南欧江七级水电站
可研阶段
选定方案
设计
Nam Ou River-7 Hydropower Project
feasibility study
selected proposal
design