摘要
2015年4月12日、4月19日昆玉钢铁公司2#、3#高炉分别在停炉165天、173天后开炉复产。本次开炉前期准备充分,开炉焦比选择准确,后续开风口、降焦比、布料角度调整紧凑合理,整个开炉过程非常顺利,实现了安全、顺利开炉、快速达产的既定目标。
After blowing off for 165 and 173 days, the blast furnace 2 and 3 of Kunyu blew on and restarted production in Apr. 12, and Apr. 19, of 2015. With full preparation before blowing on, accurate selection for blowing coke ratio, and compact and reasonable following steps: opening tuyere, reducing coke ratio and adjusting charge distributing angle, the all procedure was very smooth, the target of safe, blowing on and fast reaching the rated output is got.
作者
陈艳波
王庆鲲
蔚飞
王广林
Chen Yanbo Wang Qingkun Yu Fei Wang Guanglin(Xinjiang Kunyu Iron and Steel Co. , Ltd. , Kuitun, Xinjiang, 83320)
出处
《河北冶金》
2016年第10期38-43,共6页
Hebei Metallurgy
关键词
高炉
开炉
实践
blast furnace
blow on
practice